Case study · Sittingbourne, Kent

Cortland Mews: Full Residential Refurbishment in Sittingbourne

A complete strip-out and rebuild of a private home, from structure and services through to a new kitchen and external works, delivered by Medport Global as Principal Contractor.

Client

Private owner

Location

Sittingbourne, Kent (ME10)

Our role

Principal Contractor

Works on site

Summer 2025 to summer 2026

The brief

The owner wanted the property brought back to a high standard throughout. That meant more than a cosmetic refresh. The building needed opening up, its structure and services sorting out properly, and then finishing to a standard that would last.

They wanted one contractor to take responsibility for the whole job, rather than coordinating separate trades themselves.

What we did

We took on the project as Principal Contractor and managed every stage, from the first day of strip-out to handover.

  • Strip-out and structure. Old finishes, fittings and services removed back to the structure, with structural timber repairs and new floor joists where needed.
  • New layout. New stud partitions to create a better-organised plan.
  • Services. New heating system and boiler, with plumbing and electrics renewed through first and second fix.
  • Finishes. Plastering throughout, a new fitted kitchen, and decoration ready for occupation.
  • External works. Clearance and a new driveway and hard standing.
Strip-out and structural works in progress at Cortland Mews, Sittingbourne
Strip-out and structural works
Newly plastered bedroom ready for decoration at Cortland Mews
Plastered and ready for decoration
New fitted kitchen at Cortland Mews, Sittingbourne
New fitted kitchen
External works and new driveway at Cortland Mews, Sittingbourne
External works and driveway

How we ran it

A full strip-out always uncovers things nobody could see at survey stage. We dealt with those as they came up, talked them through with the owner, and kept the work in a sensible order so each trade could follow on from the last.

We photographed the key stages, such as structure, pipework and first-fix services, before they were covered up, so there is a clear record of what sits behind the finished walls and floors.

The result

The project was completed and handed over to the owner: a property refurbished from the structure up, with new services, a new kitchen and the external areas put right.

Planning a refurbishment in Kent or London?

We work for private owners, landlords, housing providers and councils across Kent and London. If you are weighing up a full refurbishment, we are happy to walk the property with you and talk through what it will involve.

Related

Talk to us about your property

One contractor, accountable from strip-out to handover.

Discuss your project Call 0204 5240424