Councils, housing associations and support providers are under pressure to create more supported accommodation, often from buildings that were never designed for it. A Victorian terrace, a former office or a tired hostel can make an excellent supported housing scheme, but only if the conversion is planned around the people who will live and work there.
This guide sets out the main stages of a conversion, the decisions that matter most, and the questions to ask your contractor. It draws on our experience as Principal Contractor on the Lavender Hill Rough Sleepers Hub in Wandsworth, where two Victorian terraces became an 11-bedroom supported scheme that opened in February 2026.
1. Start with how the building will be used
A supported housing scheme has three jobs at once. It must feel like a home to residents, work as an office for the staff who support them, and be safe and straightforward for the landlord to maintain. Most problems we see on conversions come from fixing the layout before the people who will run the service have been asked how they work.
Before design is fixed, agree with the support provider:
- How many residents, and what level of support they need
- Where staff will be based, and whether a staff office needs sight of entrances
- Whether you need appointment rooms, a clinical room or space for visiting professionals
- How residents will cook, eat and socialise – individual or shared facilities
- Out-of-hours arrangements, sleep-in rooms and security
At Lavender Hill, the finished hub combined bedrooms, communal living and kitchen space, reception and appointment rooms, a clinical room and a full staff floor – a layout shaped around how the service would actually run.
2. Check the building and the approvals early
Older buildings rarely match their drawings. An early measured survey and intrusive investigation reduce the risk of surprises once work starts. Alongside this, confirm:
- Planning position: whether a change of use or other consent is needed
- Building Regulations: fire safety, means of escape, accessibility and energy performance (Part L)
- Structural changes needed to create the new layout
- Condition of existing services – most conversions need new electrics, heating and fire alarm systems
- Any hazardous materials, such as asbestos, which must be surveyed before strip-out
Your appointed designers and specialists should lead on planning, building control strategy and fire strategy. Your contractor should then coordinate inspections and collect the certificates and records needed for completion.
3. Design fire safety in from the start
Supported accommodation often houses people who may need extra time or help to leave the building. Fire safety cannot be an afterthought. A typical conversion includes a new fire alarm system, compartmentation between rooms and floors, fire doors with the correct frames and closers, and fire-stopping wherever services pass through walls and floors.
Ask for evidence, not assurances. Every fire door and service penetration should be photographed before it is closed up, with product and installation records handed over in one pack. Since the Building Safety Act 2022, that record is as important as the work itself. Read more about our building safety and fire safety works.
4. Make it low-carbon and affordable to run
Supported schemes run around the clock, so running costs matter to the provider and, often, to residents. A conversion is the best moment to improve the building fabric and replace fossil-fuel heating.
At Lavender Hill we installed air source heat pumps with MCS installation certificates and heat-recovery ventilation, alongside fabric upgrades. The building reached an EPC A (score 15) rating, complying with Part L of the Building Regulations, which lowers running costs and carbon for the life of the scheme. See our decarbonisation and green retrofit work.
5. Plan the works around neighbours and residents
Many supported housing projects take place next door to, or inside, occupied buildings. Good contractors brief their site teams on safeguarding, agree access arrangements up front, and keep noise and dust to agreed times. Phasing and sequencing should be agreed with the client and support provider so the scheme can open as early as possible.
6. Insist on a complete handover
The building is only ready when the paperwork is. A good handover pack includes:
- Building Control completion certificate
- Fire alarm, emergency lighting and fire door records
- Electrical and gas or heat pump certificates (including MCS where relevant)
- Operation and maintenance (O&M) manual and as-built drawings
- Warranties and product information
Questions to ask your contractor
- Have you delivered supported accommodation before, and can we speak to that client?
- Who will be Principal Contractor under CDM 2015, and who coordinates Building Control?
- How will you record fire-safety work so we can prove it was done correctly?
- How will you manage work around residents or neighbours?
- What will be in the handover pack, and when will we receive it?
Planning a supported accommodation scheme?
Medport Global is a Constructionline Gold, SSIP-accredited Principal Contractor working with councils, housing associations and support providers across London and the South East. See our supported living work, or send us the address and a rough brief and we will come back within one working day with our first thoughts on what is possible. Call 0204 5240424 or contact us.