Councils, housing associations and support providers are under pressure to create more supported accommodation, often from buildings that were never designed for it. A Victorian terrace, a former office or a tired hostel can make an excellent supported housing scheme, but only if the conversion is planned around the people who will live and work there.

This guide sets out the main stages of a conversion, the decisions that matter most, and the questions to ask your contractor. It draws on our experience as Principal Contractor on the Lavender Hill Rough Sleepers Hub in Wandsworth, where two Victorian terraces became an 11-bedroom supported scheme that opened in February 2026.

1. Start with how the building will be used

A supported housing scheme has three jobs at once. It must feel like a home to residents, work as an office for the staff who support them, and be safe and straightforward for the landlord to maintain. Most problems we see on conversions come from fixing the layout before the people who will run the service have been asked how they work.

Before design is fixed, agree with the support provider:

At Lavender Hill, the finished hub combined bedrooms, communal living and kitchen space, reception and appointment rooms, a clinical room and a full staff floor – a layout shaped around how the service would actually run.

2. Check the building and the approvals early

Older buildings rarely match their drawings. An early measured survey and intrusive investigation reduce the risk of surprises once work starts. Alongside this, confirm:

Your appointed designers and specialists should lead on planning, building control strategy and fire strategy. Your contractor should then coordinate inspections and collect the certificates and records needed for completion.

3. Design fire safety in from the start

Supported accommodation often houses people who may need extra time or help to leave the building. Fire safety cannot be an afterthought. A typical conversion includes a new fire alarm system, compartmentation between rooms and floors, fire doors with the correct frames and closers, and fire-stopping wherever services pass through walls and floors.

Ask for evidence, not assurances. Every fire door and service penetration should be photographed before it is closed up, with product and installation records handed over in one pack. Since the Building Safety Act 2022, that record is as important as the work itself. Read more about our building safety and fire safety works.

4. Make it low-carbon and affordable to run

Supported schemes run around the clock, so running costs matter to the provider and, often, to residents. A conversion is the best moment to improve the building fabric and replace fossil-fuel heating.

At Lavender Hill we installed air source heat pumps with MCS installation certificates and heat-recovery ventilation, alongside fabric upgrades. The building reached an EPC A (score 15) rating, complying with Part L of the Building Regulations, which lowers running costs and carbon for the life of the scheme. See our decarbonisation and green retrofit work.

5. Plan the works around neighbours and residents

Many supported housing projects take place next door to, or inside, occupied buildings. Good contractors brief their site teams on safeguarding, agree access arrangements up front, and keep noise and dust to agreed times. Phasing and sequencing should be agreed with the client and support provider so the scheme can open as early as possible.

6. Insist on a complete handover

The building is only ready when the paperwork is. A good handover pack includes:

Questions to ask your contractor

Planning a supported accommodation scheme?

Medport Global is a Constructionline Gold, SSIP-accredited Principal Contractor working with councils, housing associations and support providers across London and the South East. See our supported living work, or send us the address and a rough brief and we will come back within one working day with our first thoughts on what is possible. Call 0204 5240424 or contact us.